Substation / point of interconnection ยท Ward County

#11098 Sand Lake Switch Station (SANDLAKE_5) 345kV

1 active project totalling 208 MW is queued to connect at #11098 Sand Lake Switch Station (SANDLAKE_5) 345kV in Ward County, Texas, according to ERCOT's October 2026 report.

Active capacity
208 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0255New Minglewood Energy CenterBESS208FIS Requested09/29/20290