27INR0255 · BESS · Ward County

New Minglewood Energy Center

New Minglewood Energy Center is a 208 MW battery storage project in Ward County, Texas, connecting at #11098 Sand Lake Switch Station (SANDLAKE_5) 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/29/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0255
Capacity
208 MW
Fuel
BESS (BA)
Interconnecting entity
Nova Clean Energy LLC
Projected COD
09/29/2029
Entered queue
04/29/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/29/2024
    Entered the queue with 208 MW, projected COD 09/29/2029
  • 04/29/2024
    Screening → FIS Requested