LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Starr County

80355 Del Sol 345kV

2 active projects totalling 402 MW are queued to connect at 80355 Del Sol 345kV in Starr County, Texas, according to ERCOT's October 2026 report.

Active capacity
402 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
16INR0081Mesteno WindWind202Sync Approved03/01/20270
20INR0162Diamondback solarSolar200IA Signed04/29/20280