LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
20INR0162 · Solar · Starr County

Diamondback solar

Diamondback solar is a 200 MW solar project in Starr County, Texas, connecting at 80355 Del Sol 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/29/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0162
Capacity
200 MW
Fuel
Solar (PV)
Interconnecting entity
Diamondback Solar, LLC
Projected COD
04/29/2028
Entered queue
09/13/2018
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 05/31/2028 → 04/29/2028 (-1 months)
  • 10/01/2026
    Capacity 204 → 200 MW
  • 06/30/2026
    FIS Requested → FIS Approved
  • 06/14/2024
    FIS Approved → IA Signed
  • 11/07/2018
    Screening → FIS Requested
  • 09/13/2018
    Entered the queue with 204 MW, projected COD 05/31/2028

Other projects at this substation

Mesteno WindWind202 MWSync Approved