LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
16INR0081 · Wind · Starr County

Mesteno Wind

Mesteno Wind is a 202 MW wind project in Starr County, Texas, connecting at 80355 Del Sol 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 03/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
16INR0081
Capacity
202 MW
Fuel
Wind (WT)
Interconnecting entity
Mesteno Windpower, LLC
Projected COD
03/01/2027
Entered queue
12/30/2014
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/12/2019
    Energization Approved → Sync Approved
  • 11/26/2019
    IA Signed → Energization Approved
  • 04/25/2018
    FIS Approved → IA Signed
  • 01/29/2018
    FIS Requested → FIS Approved
  • 12/30/2014
    Entered the queue with 202 MW, projected COD 03/01/2027
  • 12/30/2014
    Screening → FIS Requested

Other projects at this substation

Diamondback solarSolar200 MWIA Signed