LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection · Refugio County

tap the 345 kV Angstrom (#8249) – Static (#8676) line; AEP

1 active project totalling 511 MW is queued to connect at tap the 345 kV Angstrom (#8249) – Static (#8676) line; AEP in Refugio County, Texas, according to ERCOT's October 2026 report.

Active capacity
511 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0156Ross StorageBESS511IA Signed07/31/20270