Counties / Texas
Refugio County power projects
Refugio County, Texas has 4 active power projects totalling 2,034 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,423 MW (70%). The largest single project is Ross Solar (1,026 MW solar). 3 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
4
2.0 GW capacity
IA signed or later
3
75% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Refugio County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Ross Solar | Solar | 1,026 | tap 345kV 8249 Angstrom – 8676 Static | IA Signed | 07/31/2027 |
| Ross Storage | BESS | 511 | tap the 345 kV Angstrom (#8249) – Static (#8676) line; AEP | IA Signed | 07/31/2027 |
| Charger Solar | Solar | 397 | tap 345kV 8249 Angstrom – 5915 STP | Sync Approved | 09/18/2026 |
| Mobee Springs BESS | BESS | 101 | #8805 BONIVIEW2A 69kV | FIS Requested | 03/31/2028 |
For residents and landowners
- What power projects are planned in Refugio County?
- ERCOT's October 2026 report lists 4 active projects in Refugio County totalling 2,034 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.