1 active project totalling 703 MW is queued to connect at 345 kV Gray (Bus# 79000) in Gray County, Texas, according to ERCOT's October 2026 report.

Active capacity
703 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0080Meitner SolarSolar703IA Signed06/08/20280