25INR0080 · Solar · Gray County
Meitner Solar
Meitner Solar is a 703 MW solar project in Gray County, Texas, connecting at 345 kV Gray (Bus# 79000). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/08/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0080
- Capacity
- 703 MW
- Fuel
- Solar (PV)
- Substation
- 345 kV Gray (Bus# 79000)
- County
- Gray County
- Interconnecting entity
- IP Meitner, LLC
- Projected COD
- 06/08/2028
- Entered queue
- 07/27/2022
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/31/2024FIS Requested → IA Signed
- 07/27/2022Entered the queue with 703 MW, projected COD 06/08/2028
- 07/27/2022Screening → FIS Requested