Gray County power projects

Gray County, Texas has 3 active power projects totalling 2,121 MW in ERCOT's interconnection queue as of the October 2026 report. Wind is the largest share at 1,418 MW (67%). The largest single project is Meitner 2 Wind (709 MW wind). 2 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
3
2.1 GW capacity
IA signed or later
2
67% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Gray County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Meitner 2 WindWind70979000 Gray Substation 345kVFIS Requested06/30/2028
Meitner WindWind70979000 Gray Substation 345kVIA Signed05/24/2028
Meitner SolarSolar703345 kV Gray (Bus# 79000)IA Signed06/08/2028

For residents and landowners

What power projects are planned in Gray County?
ERCOT's October 2026 report lists 3 active projects in Gray County totalling 2,121 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.