1 active project totalling 208 MW is queued to connect at 68040 Kopperl Substation 345kV in Bosque County, Texas, according to ERCOT's October 2026 report.

Active capacity
208 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
30INR0005Woodland Energy StorageBESS208FIS Requested10/01/20300