LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
30INR0005 · BESS · Bosque County

Woodland Energy Storage

Woodland Energy Storage is a 208 MW battery storage project in Bosque County, Texas, connecting at 68040 Kopperl Substation 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/01/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
30INR0005
Capacity
208 MW
Fuel
BESS (BA)
Interconnecting entity
Woodland Energy Storage, LLC
Projected COD
10/01/2030
Entered queue
10/23/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/23/2023
    Entered the queue with 208 MW, projected COD 10/01/2030
  • 10/23/2023
    Screening → FIS Requested