27INR0449 · Solar · Brazoria County
Gulf Prairie Solar
Gulf Prairie Solar is a 202 MW solar project in Brazoria County, Texas, connecting at (CEHESub) looped either 1) on 138 kV circuit 82 between RIWOOD (#43150) and Angleton (#42110), or 2) on 345 kV circuit 18 between DOW (#42500) and Huizache (#46640). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0449
- Capacity
- 202 MW
- Fuel
- Solar (PV)
- County
- Brazoria County
- Interconnecting entity
- Gulf Prairie Energy LLC
- Projected COD
- 12/01/2028
- Entered queue
- 01/22/2025
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/22/2025Entered the queue with 202 MW, projected COD 12/01/2028
- 01/22/2025Screening → FIS Requested
Other projects at this substation
| Gulf Prairie BESS | BESS | 208 MW | FIS Requested |