27INR0371 · BESS · Glasscock County
Feather Dalea BESS
Feather Dalea BESS is a 200 MW battery storage project in Glasscock County, Texas, connecting at 59902 Sand Bluff 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/02/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0371
- Capacity
- 200 MW
- Fuel
- BESS (BA)
- Substation
- 59902 Sand Bluff 345kV
- County
- Glasscock County
- Interconnecting entity
- RWE Clean Energy Development, LLC
- Projected COD
- 07/02/2027
- Entered queue
- 09/24/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/24/2024Entered the queue with 200 MW, projected COD 07/02/2027
- 09/24/2024Screening → FIS Requested
Other projects at this substation
| Honey Mesquite Wind Farm | Wind | 174 MW | Sync Approved |
| Gardner Draw Solar | Solar | 310 MW | IA Signed |
| Indigo Quill Gas | Gas | 370 MW | FIS Requested |