26INR0447 · Wind · Glasscock County

Honey Mesquite Wind Farm

Honey Mesquite Wind Farm is a 174 MW wind project in Glasscock County, Texas, connecting at 59902 Sand Bluff 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/30/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0447
Capacity
174 MW
Fuel
Wind (WT)
Interconnecting entity
Honey Mesquite Wind Farm , LLC
Projected COD
12/30/2026
Entered queue
03/11/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/20/2026
    Energization Approved → Sync Approved
  • 08/03/2026
    IA Signed → Energization Approved
  • 09/11/2025
    FIS Requested → FIS Approved
  • 09/10/2024
    FIS Approved → IA Signed
  • 03/11/2024
    Entered the queue with 174 MW, projected COD 12/30/2026
  • 03/11/2024
    Screening → FIS Requested

Other projects at this substation

Gardner Draw SolarSolar310 MWIA Signed
Feather Dalea BESSBESS200 MWFIS Requested
Indigo Quill GasGas370 MWFIS Requested