27INR0355 · Solar · Glasscock County

Gardner Draw Solar

COD delayed 1×

Gardner Draw Solar is a 310 MW solar project in Glasscock County, Texas, connecting at 59902 Sand Bluff 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/01/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0355
Capacity
310 MW
Fuel
Solar (PV)
Interconnecting entity
RWE Clean Energy Development, LLC
Projected COD
06/01/2028
Entered queue
09/25/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 12/31/2027 → 06/01/2028 (+5 months)
  • 09/16/2026
    FIS Requested → FIS Approved
  • 08/07/2025
    FIS Approved → IA Signed
  • 09/25/2024
    Entered the queue with 310 MW, projected COD 12/31/2027
  • 09/25/2024
    Screening → FIS Requested

Other projects at this substation

Honey Mesquite Wind FarmWind174 MWSync Approved
Feather Dalea BESSBESS200 MWFIS Requested
Indigo Quill GasGas370 MWFIS Requested