27INR0355 · Solar · Glasscock County
Gardner Draw Solar
COD delayed 1×
Gardner Draw Solar is a 310 MW solar project in Glasscock County, Texas, connecting at 59902 Sand Bluff 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/01/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0355
- Capacity
- 310 MW
- Fuel
- Solar (PV)
- Substation
- 59902 Sand Bluff 345kV
- County
- Glasscock County
- Interconnecting entity
- RWE Clean Energy Development, LLC
- Projected COD
- 06/01/2028
- Entered queue
- 09/25/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 12/31/2027 → 06/01/2028 (+5 months)
- 09/16/2026FIS Requested → FIS Approved
- 08/07/2025FIS Approved → IA Signed
- 09/25/2024Entered the queue with 310 MW, projected COD 12/31/2027
- 09/25/2024Screening → FIS Requested