LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Throckmorton County power projects

Throckmorton County, Texas has 6 active power projects totalling 961 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 503 MW (52%). The largest single project is Monarch Creek Wind (283 MW wind). 1 project has signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
6
1.0 GW capacity
IA signed or later
1
17% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
6
since Sep 2026

Changes in Throckmorton County

New
10/01/2026
Sideoats Solar 1 · Solar · Throckmorton County
Entered the queue at DUSTYROAD_5 (11050) to GRHAMSES1 (1430) 345 kV. Projected COD 03/31/2031.
+168 MW
New
10/01/2026
Sideoats Solar 2 · Solar · Throckmorton County
Entered the queue at DUSTYROAD_5 (11050) to GRHAMSES1 (1430) 345kV. Projected COD 03/31/2031.
+168 MW
New
10/01/2026
Sideoats Solar 3 · Solar · Throckmorton County
Entered the queue at DUSTYROAD_5 (11050) to GRHAMSES1 (1430) 345kV. Projected COD 03/31/2031.
+168 MW
Stage change
09/15/2026
Sideoats Solar 1 · Solar · Throckmorton County
Moved from Screening to FIS Requested.
FIS Requested
Stage change
09/15/2026
Sideoats Solar 2 · Solar · Throckmorton County
Moved from Screening to FIS Requested.
FIS Requested
Stage change
09/15/2026
Sideoats Solar 3 · Solar · Throckmorton County
Moved from Screening to FIS Requested.
FIS Requested

All projects

ProjectFuelMWSubstationStageCOD
Monarch Creek WindWind28311419 Coody Crossing Switch 345kVIA Signed09/17/2027
Sideoats Solar 1Solar168DUSTYROAD_5 (11050) to GRHAMSES1 (1430) 345 kVFIS Requested03/31/2031
Sideoats Solar 2Solar168DUSTYROAD_5 (11050) to GRHAMSES1 (1430) 345kVFIS Requested03/31/2031
Sideoats Solar 3Solar168DUSTYROAD_5 (11050) to GRHAMSES1 (1430) 345kVFIS Requested03/31/2031
Sleepy Hollow BESSBESS123Tap 138 kV 792 Murray - 6169 Paint CreekFIS Approved02/22/2028
Ayass BESSBESS516206 Bush Knob 69kVFIS Requested12/30/2028
Lonesome Dove BESSBESS256Not listedWithdrawnn/a
Leaning Tree BESSBESS256Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Throckmorton County?
ERCOT's October 2026 report lists 6 active projects in Throckmorton County totalling 961 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.