Substation / point of interconnection ยท Throckmorton County
6206 Bush Knob 69kV
1 active project totalling 51 MW is queued to connect at 6206 Bush Knob 69kV in Throckmorton County, Texas, according to ERCOT's October 2026 report.
Active capacity
51 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
69 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0558 | Ayass BESS | BESS | 51 | FIS Requested | 12/30/2028 | 0 |