Counties / Texas
Swisher County power projects
Swisher County, Texas has 7 active power projects totalling 2,049 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 904 MW (44%). The largest single project is Commodus 2 Wind (642 MW wind). 2 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
7
2.0 GW capacity
IA signed or later
2
29% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Swisher County
COD change
10/01/2026
Hornet Energy Storage SLF · BESS · Swisher County
Projected COD moved 09/30/2028 → 09/30/2029. Delay #1 for this project.
+12 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Commodus 2 Wind | Wind | 642 | Tapping the 345 kV Double-Circuit Line from Tule Canyon (Bus# 23914) to Alibates (Bus# 23900) | FIS Requested | 07/30/2029 |
| Frye Storage | BESS | 504 | new 345kV sub Kress connecting both 23912 Ogallala - 23914 Tule Canyon circuits | FIS Requested | 12/01/2028 |
| Commodus 2 Solar | Solar | 502 | Tapping the 345 kV Double-Circuit Line from Tule Canyon (Bus# 23914) to Alibates (Bus# 23900) | FIS Requested | 07/30/2029 |
| Hornet Solar II SLF | Solar | 202 | Ozark Trail Switch 345kV substation (Bus #23901) | IA Signed | 07/31/2028 |
| Stem Solar | Solar | 200 | tap 345kV 23914 Tule Canyon - 23912 Ogallala | FIS Requested | 08/26/2025 |
| Hornet Storage II SLF | BESS | 0 | Ozark Trail Switch 345kV substation (Bus #23901) | IA Signed | 07/31/2028 |
| Hornet Energy Storage SLF | BESS | 0 | 23901 OZARKTRAIL_5 345kV | FIS Requested | 09/30/2029 |
For residents and landowners
- What power projects are planned in Swisher County?
- ERCOT's October 2026 report lists 7 active projects in Swisher County totalling 2,049 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.