ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0003 · Solar · Swisher County

Stem Solar

COD date passed

Stem Solar is a 200 MW solar project in Swisher County, Texas, connecting at tap 345kV 23914 Tule Canyon - 23912 Ogallala. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 08/26/2025. Its projected COD of 08/26/2025 has already passed without ERCOT approval to synchronize, so the date is likely to move.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0003
Capacity
200 MW
Fuel
Solar (PV)
Interconnecting entity
Innovative Solar 134, LLC
Projected COD
08/26/2025
Entered queue
02/04/2020
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/22/2020
    Screening → FIS Requested
  • 02/04/2020
    Entered the queue with 200 MW, projected COD 08/26/2025

Other projects at this substation

No other projects at this substation.