Counties / Texas
Sterling County power projects
Sterling County, Texas has 7 active power projects totalling 1,288 MW in ERCOT's interconnection queue as of the October 2026 report. Wind is the largest share at 575 MW (45%). The largest single project is Goat Mountain Wind-Repower (303 MW wind). 3 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
7
1.3 GW capacity
IA signed or later
3
43% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Sterling County
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Goat Mountain Wind-Repower | Wind | 303 | 76030 Gasconades Creek 345kV | IA Signed | 03/01/2027 |
| Bob Creek Wind | Wind | 240 | 59902 Sand Bluff 345kV | IA Signed | 07/01/2028 |
| Roan Solar Phase 1 | Solar | 206 | Divide (#76090) to Sand Bluff Wind Farm (#59902) 345 kV | FIS Requested | 04/30/2029 |
| Roan Solar Phase 2 | Solar | 206 | Divide (#76090) to Sand Bluff Wind Farm (#59902) 345 kV | FIS Requested | 12/15/2029 |
| Goat Mountain BESS | BESS | 201 | 76030-Gasconades Creek 345 kV | FIS Requested | 06/01/2028 |
| Goat Mountain BESS 2 | BESS | 101 | 76030-Gasconades Creek 345 kV | FIS Requested | 06/01/2028 |
| Capricorn I & III repower | Wind | 32 | 180757 Capricorn Ridge 3 138kV | Sync Approved | 06/30/2026 |
For residents and landowners
- What power projects are planned in Sterling County?
- ERCOT's October 2026 report lists 7 active projects in Sterling County totalling 1,288 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.