Substation / point of interconnection ยท Sterling County
Divide (#76090) to Sand Bluff Wind Farm (#59902) 345 kV
2 active projects totalling 412 MW are queued to connect at Divide (#76090) to Sand Bluff Wind Farm (#59902) 345 kV in Sterling County, Texas, according to ERCOT's October 2026 report.
Active capacity
412 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0185 | Roan Solar Phase 1 | Solar | 206 | FIS Requested | 04/30/2029 | 0 |
| 29INR0187 | Roan Solar Phase 2 | Solar | 206 | FIS Requested | 12/15/2029 | 0 |