2 active projects totalling 412 MW are queued to connect at Divide (#76090) to Sand Bluff Wind Farm (#59902) 345 kV in Sterling County, Texas, according to ERCOT's October 2026 report.

Active capacity
412 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
29INR0185Roan Solar Phase 1Solar206FIS Requested04/30/20290
29INR0187Roan Solar Phase 2Solar206FIS Requested12/15/20290