ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Somervell County power projects

Somervell County, Texas has 2 active power projects totalling 666 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 495 MW (74%). The largest single project is Black Mountain Somervell Gas Combined (495 MW natural gas). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
2
0.7 GW capacity
IA signed or later
1
50% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Somervell County

Stage change
09/17/2026
Yellow Viking Solar · Solar · Somervell County
Moved from FIS Requested to FIS Approved.
FIS Approved

All projects

For residents and landowners

What power projects are planned in Somervell County?
ERCOT's October 2026 report lists 2 active projects in Somervell County totalling 666 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.