21INR0520 · Solar · Somervell County
Yellow Viking Solar
Yellow Viking Solar is a 171 MW solar project in Somervell County, Texas, connecting at Tap 345kV 1900 Comanche Peak - 11886 Timberview Switch. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/13/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 21INR0520
- Capacity
- 171 MW
- Fuel
- Solar (PV)
- County
- Somervell County
- Interconnecting entity
- Yellow Viking Development One, LLC
- Projected COD
- 07/13/2027
- Entered queue
- 08/20/2020
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/17/2026FIS Requested → FIS Approved
- 10/25/2022FIS Approved → IA Signed
- 08/20/2020Entered the queue with 171 MW, projected COD 07/13/2027
- 08/20/2020Screening → FIS Requested
Other projects at this substation
No other projects at this substation.