ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Mcmullen County power projects

Mcmullen County, Texas has 1 active power project totalling 262 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 262 MW (100%). The largest single project is Miranda Solar Project (262 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
1
0.3 GW capacity
IA signed or later
1
100% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Mcmullen County

MW change
10/01/2026
Miranda Solar Project · Solar · Mcmullen County
Requested capacity increased.
261 → 262 MW

All projects

ProjectFuelMWSubstationStageCOD
Miranda Solar ProjectSolar262Tap 345kV 5709 Fowlerton - 5901 San Miguel Ckt 1IA Signed12/06/2027

For residents and landowners

What power projects are planned in Mcmullen County?
ERCOT's October 2026 report lists 1 active project in Mcmullen County totalling 262 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.