Miranda Solar Project is a 262 MW solar project in Mcmullen County, Texas, connecting at Tap 345kV 5709 Fowlerton - 5901 San Miguel Ckt 1. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/06/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0161
- Capacity
- 262 MW
- Fuel
- Solar (PV)
- County
- Mcmullen County
- Interconnecting entity
- Miranda Solar Project, LLC
- Projected COD
- 12/06/2027
- Entered queue
- 11/03/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Capacity 261 → 262 MW
- 09/03/2024FIS Requested → FIS Approved
- 07/16/2024FIS Approved → IA Signed
- 06/22/2022Screening → FIS Requested
- 11/03/2021Entered the queue with 261 MW, projected COD 12/06/2027