Counties / Texas
Knox County power projects
Knox County, Texas has 8 active power projects totalling 1,861 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,228 MW (66%). The largest single project is Oriole Solar (504 MW solar). 4 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.
Active projects
8
1.9 GW capacity
IA signed or later
4
50% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Knox County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Oriole Solar | Solar | 504 | Tap 345kV 6076 Foxtail - 60791 Perigee | IA Signed | 12/29/2028 |
| Zeissel Solar | Solar | 452 | #60094 Joule 345kV | IA Signed | 06/30/2028 |
| West Munday Wind | Wind | 352 | Tap 345kV 60703 Gauss7D – 60712 Quasar | IA Signed | 08/31/2029 |
| Wagon Timber Solar | Solar | 172 | 6110 Munday East 138kV | FIS Requested | 09/03/2029 |
| Oriole BES | BESS | 150 | Tap 345kV 6076 Foxtail - 60791 Perigee | IA Signed | 12/29/2028 |
| Lemma Solar | Solar | 101 | 6088 Benjamin AEP 138kV | FIS Requested | 07/01/2028 |
| Knox County Moore Storage | BESS | 77 | 6110 Munday East Substation 138kV | FIS Requested | 06/30/2028 |
| Wagon Timber Storage | BESS | 54 | 6110 Munday East 138kV | FIS Requested | 09/03/2029 |
| Sundance Solar | Solar | 301 | Not listed | Withdrawn | n/a |
| Zeissel Storage SLF | BESS | 0 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Knox County?
- ERCOT's October 2026 report lists 8 active projects in Knox County totalling 1,861 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.