28INR0008 · Solar · Knox County
Oriole Solar
Oriole Solar is a 504 MW solar project in Knox County, Texas, connecting at Tap 345kV 6076 Foxtail - 60791 Perigee. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/29/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0008
- Capacity
- 504 MW
- Fuel
- Solar (PV)
- Substation
- Tap 345kV 6076 Foxtail - 60791 Perigee
- County
- Knox County
- Interconnecting entity
- Rolling Plains Solar
- Projected COD
- 12/29/2028
- Entered queue
- 05/09/2023
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/08/2025FIS Requested → IA Signed
- 05/09/2023Entered the queue with 504 MW, projected COD 12/29/2028
- 05/09/2023Screening → FIS Requested
Other projects at this substation
| Oriole BES | BESS | 150 MW | IA Signed |