26INR0617 · BESS · Knox County
Knox County Moore Storage
Knox County Moore Storage is a 77 MW battery storage project in Knox County, Texas, connecting at 6110 Munday East Substation 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0617
- Capacity
- 77 MW
- Fuel
- BESS (BA)
- Substation
- 6110 Munday East Substation 138kV
- County
- Knox County
- Interconnecting entity
- DM-KCM, LLC
- Projected COD
- 06/30/2028
- Entered queue
- 12/13/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/13/2024Entered the queue with 77 MW, projected COD 06/30/2028
- 12/13/2024Screening → FIS Requested
Other projects at this substation