Counties / Texas
Hood County power projects
Hood County, Texas has 4 active power projects totalling 761 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 307 MW (40%). The largest single project is Wolf Hollow III (306 MW natural gas). 3 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
4
0.8 GW capacity
IA signed or later
3
75% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
3
since Sep 2026
Changes in Hood County
Stage change
09/18/2026
Energization Approved
Stage change
09/16/2026
IA Signed
Stage change
09/16/2026
IA Signed
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Wolf Hollow III | Gas | 306 | 1877 Mitchell Bend 345KV | FIS Requested | 05/31/2027 |
| Apache Hill BESS | BESS | 201 | 363 Hood 138kV | Energization Approved | 10/31/2026 |
| Rain Lily Solar 1 | Solar | 148 | Tap 138kV #350 ABBYBEND - #363 HOOD | IA Signed | 10/15/2028 |
| Rain Lily Storage 1 | BESS | 106 | Tap 138kV #350 ABBYBEND - #363 HOOD | IA Signed | 10/15/2028 |
For residents and landowners
- What power projects are planned in Hood County?
- ERCOT's October 2026 report lists 4 active projects in Hood County totalling 761 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.