LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0567 · Gas · Hood County

Wolf Hollow III

Wolf Hollow III is a 306 MW natural gas project in Hood County, Texas, connecting at 1877 Mitchell Bend 345KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/31/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0567
Capacity
306 MW
Fuel
Gas (GT)
Interconnecting entity
Wolf Hollow II Power LLC
Projected COD
05/31/2027
Entered queue
05/30/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/30/2023
    Entered the queue with 306 MW, projected COD 05/31/2027
  • 05/30/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.