Counties / Texas
Henderson County power projects
Henderson County, Texas has 6 active power projects totalling 1,189 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 1,088 MW (92%). The largest single project is Wild Paw Storage (301 MW battery storage). 2 projects have signed an interconnection agreement or reached a later stage. 4 projects in the county are listed as withdrawn or cancelled.
Active projects
6
1.2 GW capacity
IA signed or later
2
33% of active projects
Withdrawn or cancelled
4
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Henderson County
MW change
10/01/2026
313 → 301 MW
Stage change
09/21/2026
FIS Approved
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Wild Paw Storage | BESS | 301 | Tap 345kV 3124 Trinidad - 3130 Forest Grove | FIS Requested | 09/30/2028 |
| Old Fiddler Energy Storage | BESS | 225 | 3233 Foggle Switch 138 kV | Screening | 04/16/2029 |
| Anatole Renewable Energy Storage | BESS | 208 | (Bus# 6951) Eustace Southeast 138kV Substation (owned by Rayburn Electric Cooperative) | IA Signed | 06/30/2027 |
| Sloan Storage | BESS | 201 | 3179 Pauline 138kV | FIS Requested | 03/27/2026 |
| Kit Fox Storage | BESS | 154 | Walton Switch (6899) 138KV | FIS Requested | 07/01/2029 |
| Musgravite Solar | Solar | 101 | Tap 138 kV (6855) Coffee - (6849) New York. | IA Signed | 11/01/2027 |
| Brittlebush BESS | BESS | 597 | Not listed | Withdrawn | n/a |
| Brittlebush Solar | Solar | 594 | Not listed | Withdrawn | n/a |
| Dodd Solar I | Solar | 202 | Not listed | Withdrawn | n/a |
| Trinidad ESS Addition | BESS | 110 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Henderson County?
- ERCOT's October 2026 report lists 6 active projects in Henderson County totalling 1,189 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.