Henderson County power projects

Henderson County, Texas has 6 active power projects totalling 1,189 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 1,088 MW (92%). The largest single project is Wild Paw Storage (301 MW battery storage). 2 projects have signed an interconnection agreement or reached a later stage. 4 projects in the county are listed as withdrawn or cancelled.

Active projects
6
1.2 GW capacity
IA signed or later
2
33% of active projects
Withdrawn or cancelled
4
listed by ERCOT
Changes tracked
2
since Sep 2026

Changes in Henderson County

MW change
10/01/2026
Wild Paw Storage · BESS · Henderson County
Requested capacity reduced.
313 → 301 MW
Stage change
09/21/2026
Anatole Renewable Energy Storage · BESS · Henderson County
Moved from FIS Requested to FIS Approved.
FIS Approved

All projects

ProjectFuelMWSubstationStageCOD
Wild Paw StorageBESS301Tap 345kV 3124 Trinidad - 3130 Forest GroveFIS Requested09/30/2028
Old Fiddler Energy StorageBESS2253233 Foggle Switch 138 kVScreening04/16/2029
Anatole Renewable Energy StorageBESS208(Bus# 6951) Eustace Southeast 138kV Substation (owned by Rayburn Electric Cooperative)IA Signed06/30/2027
Sloan StorageBESS2013179 Pauline 138kVFIS Requested03/27/2026
Kit Fox StorageBESS154Walton Switch (6899) 138KVFIS Requested07/01/2029
Musgravite SolarSolar101Tap 138 kV (6855) Coffee - (6849) New York.IA Signed11/01/2027
Brittlebush BESSBESS597Not listedWithdrawnn/a
Brittlebush SolarSolar594Not listedWithdrawnn/a
Dodd Solar ISolar202Not listedWithdrawnn/a
Trinidad ESS AdditionBESS110Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Henderson County?
ERCOT's October 2026 report lists 6 active projects in Henderson County totalling 1,189 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.