Substation / point of interconnection ยท Henderson County
Tap 138 kV (6855) Coffee - (6849) New York.
1 active project totalling 101 MW is queued to connect at Tap 138 kV (6855) Coffee - (6849) New York. in Henderson County, Texas, according to ERCOT's October 2026 report.
Active capacity
101 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0198 | Musgravite Solar | Solar | 101 | IA Signed | 11/01/2027 | 0 |