LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Henderson County

Tap 138 kV (6855) Coffee - (6849) New York.

1 active project totalling 101 MW is queued to connect at Tap 138 kV (6855) Coffee - (6849) New York. in Henderson County, Texas, according to ERCOT's October 2026 report.

Active capacity
101 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0198Musgravite SolarSolar101IA Signed11/01/20270