Counties / Texas
Hays County power projects
Hays County, Texas has 5 active power projects totalling 147 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 75 MW (51%). The largest single project is PaleAle BESS (75 MW battery storage). 0 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
5
0.1 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
4
since Sep 2026
Changes in Hays County
COD change
10/01/2026
Hays Energy Unit 3 Repower · Gas · Hays County
Projected COD moved 07/01/2027 → 07/01/2028. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Hays Energy Unit 2 Repower · Gas · Hays County
Projected COD moved 07/01/2027 → 07/01/2028. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Hays Energy Unit 1 Repower · Gas · Hays County
Projected COD moved 07/01/2027 → 07/01/2028. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Hays Energy Unit 4 Repower · Gas · Hays County
Projected COD moved 07/01/2027 → 07/01/2028. Delay #1 for this project.
+12 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| PaleAle BESS | BESS | 75 | Tap 138 kV Bus 7506 L_CEDAVA8_1Y - Bus 7507 L_FRIEND8_1Y | FIS Approved | 04/15/2027 |
| Hays Energy Unit 3 Repower | Gas | 18 | 7043 Hays 345kV | FIS Requested | 07/01/2028 |
| Hays Energy Unit 2 Repower | Gas | 18 | 7043 Haysen 345kV | FIS Requested | 07/01/2028 |
| Hays Energy Unit 1 Repower | Gas | 18 | 7043 Hays Energy 345kV | FIS Requested | 07/01/2028 |
| Hays Energy Unit 4 Repower | Gas | 18 | 7043 Hays Energy 345kV | FIS Requested | 07/01/2028 |
For residents and landowners
- What power projects are planned in Hays County?
- ERCOT's October 2026 report lists 5 active projects in Hays County totalling 147 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.