Substation / point of interconnection ยท Hays County
Tap 138 kV Bus 7506 L_CEDAVA8_1Y - Bus 7507 L_FRIEND8_1Y
1 active project totalling 75 MW is queued to connect at Tap 138 kV Bus 7506 L_CEDAVA8_1Y - Bus 7507 L_FRIEND8_1Y in Hays County, Texas, according to ERCOT's October 2026 report.
Active capacity
75 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0387 | PaleAle BESS | BESS | 75 | FIS Approved | 04/15/2027 | 0 |