LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Zapata County

345 kV Rapido Substation (New ETT Substation) tapping the existing 345 kV Line from CENIZO7C (#80225) to DELSOL7C (#80307).

2 active projects totalling 396 MW are queued to connect at 345 kV Rapido Substation (New ETT Substation) tapping the existing 345 kV Line from CENIZO7C (#80225) to DELSOL7C (#80307). in Zapata County, Texas, according to ERCOT's October 2026 report.

Active capacity
396 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
23INR0561Cascabel Wind 2Wind198IA Signed12/01/20270
24INR0424Cascabel Wind 1Wind198IA Signed12/01/20270