LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0561 · Wind · Zapata County

Cascabel Wind 2

Cascabel Wind 2 is a 198 MW wind project in Zapata County, Texas, connecting at 345 kV Rapido Substation (New ETT Substation) tapping the existing 345 kV Line from CENIZO7C (#80225) to DELSOL7C (#80307).. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0561
Capacity
198 MW
Fuel
Wind (WT)
Interconnecting entity
Vaquero Wind Energy, LLC
Projected COD
12/01/2027
Entered queue
02/15/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/23/2025
    FIS Requested → IA Signed
  • 02/15/2023
    Entered the queue with 198 MW, projected COD 12/01/2027
  • 02/15/2023
    Screening → FIS Requested

Other projects at this substation

Cascabel Wind 1Wind198 MWIA Signed