LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Wichita County

Tap 345kV 1730 Krum West Swtich - 6111 Riley7B

2 active projects totalling 182 MW are queued to connect at Tap 345kV 1730 Krum West Swtich - 6111 Riley7B in Wichita County, Texas, according to ERCOT's October 2026 report.

Active capacity
182 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0154Nymphaea SolarSolar121IA Signed07/01/20280
25INR0155Nymphaea StorageBESS61IA Signed07/01/20280