25INR0154 · Solar · Wichita County

Nymphaea Solar

Nymphaea Solar is a 121 MW solar project in Wichita County, Texas, connecting at Tap 345kV 1730 Krum West Swtich - 6111 Riley7B. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0154
Capacity
121 MW
Fuel
Solar (PV)
Interconnecting entity
Nymphaea Solar, LLC
Projected COD
07/01/2028
Entered queue
09/21/2022
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/18/2026
    FIS Requested → IA Signed
  • 12/23/2022
    Screening → FIS Requested
  • 09/21/2022
    Entered the queue with 121 MW, projected COD 07/01/2028

Other projects at this substation

Nymphaea StorageBESS61 MWIA Signed