80219 Lobo 345kV
3 active projects totalling 816 MW are queued to connect at 80219 Lobo 345kV in Webb County, Texas, according to ERCOT's October 2026 report.
Active capacity
816 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0077 | Cuchillas BESS | BESS | 307 | FIS Requested | 12/15/2028 | 0 |
| 24INR0059 | Cuchillas Solar | Solar | 306 | IA Signed | 12/15/2028 | 0 |
| 22INR0257 | Corazon Solar Phase II | Solar | 204 | IA Signed | 06/01/2028 | 0 |