LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0059 · Solar · Webb County

Cuchillas Solar

Cuchillas Solar is a 306 MW solar project in Webb County, Texas, connecting at 80219 Lobo 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0059
Capacity
306 MW
Fuel
Solar (PV)
Interconnecting entity
Gransolar Texas Two, LLC
Projected COD
12/15/2028
Entered queue
06/02/2021
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/27/2025
    FIS Requested → FIS Approved
  • 06/20/2023
    FIS Approved → IA Signed
  • 02/11/2022
    Screening → FIS Requested
  • 06/02/2021
    Entered the queue with 306 MW, projected COD 12/15/2028

Other projects at this substation

Corazon Solar Phase IISolar204 MWIA Signed
Cuchillas BESSBESS307 MWFIS Requested