24INR0059 · Solar · Webb County
Cuchillas Solar
Cuchillas Solar is a 306 MW solar project in Webb County, Texas, connecting at 80219 Lobo 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0059
- Capacity
- 306 MW
- Fuel
- Solar (PV)
- Substation
- 80219 Lobo 345kV
- County
- Webb County
- Interconnecting entity
- Gransolar Texas Two, LLC
- Projected COD
- 12/15/2028
- Entered queue
- 06/02/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/27/2025FIS Requested → FIS Approved
- 06/20/2023FIS Approved → IA Signed
- 02/11/2022Screening → FIS Requested
- 06/02/2021Entered the queue with 306 MW, projected COD 12/15/2028
Other projects at this substation
| Corazon Solar Phase II | Solar | 204 MW | IA Signed |
| Cuchillas BESS | BESS | 307 MW | FIS Requested |