LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Starr County

8795 Roma 138kV

2 active projects totalling 137 MW are queued to connect at 8795 Roma 138kV in Starr County, Texas, according to ERCOT's October 2026 report.

Active capacity
137 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
20INR0216Starr Solar RanchSolar137Sync Approved08/14/20250
25INR0379Starr StorageBESS0FIS Requested03/29/20280