25INR0379 · BESS · Starr County
Starr Storage
Starr Storage is a 0 MW battery storage project in Starr County, Texas, connecting at 8795 Roma 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/29/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0379
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- 8795 Roma 138kV
- County
- Starr County
- Interconnecting entity
- Falcon Lake Storage, LLC
- Projected COD
- 03/29/2028
- Entered queue
- 03/08/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/08/2023Entered the queue with 0 MW, projected COD 03/29/2028
- 03/08/2023Screening → FIS Requested
Other projects at this substation
| Starr Solar Ranch | Solar | 137 MW | Sync Approved |