Substation / point of interconnection ยท Pecos County
Tap 345kV 60404 Solstice to 38441 Bottlebrush
5 active projects totalling 1,513 MW are queued to connect at Tap 345kV 60404 Solstice to 38441 Bottlebrush in Pecos County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,513 MW
queued at this substation
Active projects
5
5 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0347 | Glass Mountain BB Solar 1 | Solar | 303 | FIS Requested | 03/01/2029 | 0 |
| 29INR0348 | Glass Mountain BB Solar 2 | Solar | 303 | FIS Requested | 03/01/2029 | 0 |
| 29INR0349 | Glass Mountain BB Solar 5 | Solar | 303 | FIS Requested | 10/01/2029 | 0 |
| 29INR0357 | Glass Mountain BB Solar 3 | Solar | 303 | FIS Requested | 10/01/2029 | 0 |
| 29INR0358 | Glass Mountain BB Solar 4 | Solar | 303 | FIS Requested | 10/01/2029 | 0 |