29INR0357 · Solar · Pecos County
Glass Mountain BB Solar 3
Glass Mountain BB Solar 3 is a 303 MW solar project in Pecos County, Texas, connecting at Tap 345kV 60404 Solstice to 38441 Bottlebrush. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0357
- Capacity
- 303 MW
- Fuel
- Solar (PV)
- County
- Pecos County
- Interconnecting entity
- Glass Mountain Solar III, LLC
- Projected COD
- 10/01/2029
- Entered queue
- 05/29/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/29/2026Entered the queue with 303 MW, projected COD 10/01/2029
- 05/29/2026Screening → FIS Requested
Other projects at this substation
| Glass Mountain BB Solar 1 | Solar | 303 MW | FIS Requested |
| Glass Mountain BB Solar 2 | Solar | 303 MW | FIS Requested |
| Glass Mountain BB Solar 5 | Solar | 303 MW | FIS Requested |