Substation / point of interconnection ยท Pecos County

60400 Lynx 138kV

3 active projects totalling 162 MW are queued to connect at 60400 Lynx 138kV in Pecos County, Texas, according to ERCOT's October 2026 report.

Active capacity
162 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
29INR0287Valentine Energy CenterGas162FIS Requested02/28/20310
18INR0079Woodward I repowerWind0Sync Approved12/31/20260
18INR0080Woodward 2 repowerWind0Sync Approved12/31/20260