18INR0079 · Wind · Pecos County
Woodward I repower
Woodward I repower is a 0 MW wind project in Pecos County, Texas, connecting at 60400 Lynx 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 18INR0079
- Capacity
- 0 MW
- Fuel
- Wind (WT)
- Substation
- 60400 Lynx 138kV
- County
- Pecos County
- Interconnecting entity
- Nextera
- Projected COD
- 12/31/2026
- Entered queue
- 06/27/2018
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/13/2019Energization Approved → Sync Approved
- 11/07/2019IA Signed → Energization Approved
- 01/09/2019FIS Requested → FIS Approved
- 12/12/2018FIS Approved → IA Signed
- 06/27/2018Entered the queue with 0 MW, projected COD 12/31/2026
- 06/27/2018Screening → FIS Requested
Other projects at this substation
| Woodward 2 repower | Wind | 0 MW | Sync Approved |
| Valentine Energy Center | Gas | 162 MW | FIS Requested |