1 active project totalling 108 MW is queued to connect at Tap #331 Rwmiller - #320 Jaybird 138kV in Palo Pinto County, Texas, according to ERCOT's October 2026 report.

Active capacity
108 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0482Vault SolarSolar108IA Signed12/31/20270