Palo Pinto County power projects
Palo Pinto County, Texas has 3 active power projects totalling 315 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 315 MW (100%). The largest single project is Vault Solar (108 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
3
0.3 GW capacity
IA signed or later
1
33% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Palo Pinto County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Vault Solar | Solar | 108 | Tap #331 Rwmiller - #320 Jaybird 138kV | IA Signed | 12/31/2027 |
| McClure Solar | Solar | 106 | tap 69kV 785 Oran - 343 Morris Sheppard | FIS Requested | 12/31/2025 |
| Pollo Pinto Solar | Solar | 101 | Tap 138kV 331 RWMILLER - 320 JAYBIRD | FIS Approved | 02/24/2029 |
For residents and landowners
- What power projects are planned in Palo Pinto County?
- ERCOT's October 2026 report lists 3 active projects in Palo Pinto County totalling 315 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.