Substation / point of interconnection ยท Nueces County
138KV Tap 8921 Terra Verde - 8518 Kingsville
1 active project totalling 125 MW is queued to connect at 138KV Tap 8921 Terra Verde - 8518 Kingsville in Nueces County, Texas, according to ERCOT's October 2026 report.
Active capacity
125 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0329 | Lynx Energy Storage | BESS | 125 | Sync Approved | 05/01/2026 | 0 |